Developer/Owner:Owner: City of Fort Collins Right of Way / Developer: City of Fort Collins Street and Stormwater
URA funding:$4,750,000
Total cost:$14,198,000
Development of the West side of College Avenue north of Vine Street has lagged behind the rest of the area due to inadequate stormwater and street circulation. This project will correct those deficiencies by adding storm drainage lines under Mason Street and stormwater detention facilities in the vicinity. As an added bonus, it establishes Mason Street as a viable street for traffic circulation in the area.
This project will advance the project on a shorter schedule than originally anticipated by paying for early phase project costs engineering, design, and right-of-way acquisition.
FAQs
ROW acquisition is anticipated for late 2026 and construction beginning in 2028.
Better infrastructure allows blight elimination and positive development along the west side of College Avenue. This has been a need long advocated by the community.
Storm water can be controlled in the area without development giving up large parts of the developable lots for detention during storms.
Project details
In Progress
Mason Street from Alpine to Hickory Street
Developer/Owner:Owner: City of Fort Collins Right of Way / Developer: City of Fort Collins Street and Stormwater